If your application meets one or both of the below criteria, you need to include a drainage plan. Please note that Fast Track applications do not require a drainage plan as part of the application.
Where the application shows below ground/in ground slab drainage, a drainage plan is required for approval.
Where the application shows above ground sanitary drainage, a drainage plan is required for approval. Total length of sanitary drainage includes stacks, EPW risers, and excludes lengths of fixture discharge pipes and vents.
Note: Where electronic lodgement is not used, and the submitted documentation is larger than A3 document size, four copies of the larger documentation is required for all applications.
The scaled site plans/floor plans are required to show:
The on-site sewerage facility (OSSF) design and site and soil evaluation report must be completed by a qualified OSSF designer registered with Council, and be in accordance with the Queensland Plumbing and Wastewater Code and AS/NZS 1547:2000. The design must show:
The scaled, site plans/floor plans are required to show:
All hydraulic plans submitted to Council’s Hydraulics Unit for plumbing or drainage assessment must be completed to the following minimum standards before approval of the plans will be considered:
Hydraulic plans are to be drafted to the minimum drafting standard and requirements, with the addition of:
Hydraulic plans are to be drafted to the minimum drafting standards and requirements, taking note of the following: